Buyers of under-construction flats in Bangalore are often offered two ways to pay. One is a regular home loan released in stages as the building rises. The other is a builder scheme with a small payment now and little or nothing to pay until possession. This guide explains how each route works, what the regulators have said about builder-paid interest, and how to compare the real cost.
How a Regular Construction-Linked Loan Works
In a construction-linked plan, the price is paid in instalments tied to milestones such as the foundation, each floor slab and the finishing work. The bank releases the loan to the developer in the same stages, after its engineer confirms the progress. The buyer first pays the margin, which the Reserve Bank of India sets through loan-to-value limits.
The limits on what a lender may fund are as follows:
- Up to 90% of the value for a home loan of up to Rs. 30 Lakhs
- Up to 80% for a loan above Rs. 30 Lakhs and up to Rs. 75 Lakhs
- Up to 75% for a loan above Rs. 75 Lakhs
Until the last tranche is released, most lenders collect only the interest on the amount paid out so far. This is called pre-EMI interest, and it rises as each stage is funded. The full EMI begins once the loan is fully disbursed, usually around possession.
What Builder Financing Means
Builder financing is a loose term that covers two different products. The difference between them matters more than the headline ratio in the advertisement.
Deferred payment plans
In a deferred plan such as 20:80, 10:10:80 or 20:20:60, the buyer pays a small share at booking and the largest share close to possession. The developer funds the construction in between, so a loan is needed only near the end. The buyer carries very little interest during the build, and the money at risk before handover stays small.
The cost of that comfort is usually in the price. A developer who waits three or four years for most of the money often quotes a higher rate per sq ft on this plan than on a construction-linked plan. Asking for both price sheets for the same flat shows the gap clearly.
Interest subvention schemes
In a subvention scheme, the buyer takes a home loan at the start and signs a three-way agreement with the bank and the developer. The bank pays out most of the loan early, and the developer promises to pay the pre-EMI interest until possession or for a fixed period. The buyer pays 5% to 20% up front and expects to pay nothing more until the flat is ready.
The loan in such a scheme is in the buyer's name from the first day. If the developer stops paying the interest, the bank turns to the buyer. A missed payment then appears on the buyer's credit record, even though the flat is unfinished.
What the Regulators Have Said
The Reserve Bank of India addressed these schemes in a circular of 3 September 2013. It told banks to link the release of housing loans closely to the stages of construction. It also told them to avoid upfront disbursal for incomplete, under-construction and greenfield projects.
The National Housing Bank followed on 19 July 2019 with a direction to housing finance companies. It asked them to stop offering loan products in which the developer services the loan on behalf of the borrower. It repeated that disbursal must follow the progress of construction.
The courts have since examined how such loans were given. In April 2025 the Supreme Court directed the Central Bureau of Investigation to open preliminary enquiries into the conduct of builders and lenders in subvention schemes. In September 2025 the agency registered six further cases covering projects in Mumbai, Bangalore and Kolkata, and carried out searches in the three cities.
A Worked Comparison
Take a flat priced at Rs. 1.5 Crore, with a loan of Rs. 1.125 Crore, the 75% limit for a loan above Rs. 75 Lakhs, at 8.5% a year and a three-year build. The figures below are illustrations, since the rate and the milestone schedule differ from one loan to the next.
| Item | Construction-linked loan | Subvention with early disbursal |
|---|---|---|
| Loan released | Six equal tranches, one every six months | Full Rs. 1.125 Crore at the start |
| Interest during the three-year build | About Rs. 16.7 Lakhs | About Rs. 28.7 Lakhs |
| Who pays that interest | The buyer, month by month | The developer, as long as it keeps paying |
| Bank money with the developer if work stops in year one | Rs. 18.75 Lakhs to Rs. 37.5 Lakhs | Rs. 1.125 Crore |
| EMI after possession (20 years) | About Rs. 97,600 a month | About Rs. 97,600 a month |
The table shows why the scheme carries more risk than its monthly comfort suggests. Early disbursal creates about Rs. 12 Lakhs of extra interest, and the developer recovers that cost through the price. If the project is delayed beyond the promised period, interest of about Rs. 79,700 a month falls on the buyer.
In the construction-linked route the buyer pays interest during the build, but only on money that matches work done. The bank's stage checks also act as a second pair of eyes on progress. A stalled project leaves a smaller loan to settle.
Tax Treatment of Interest Before Possession
Interest paid before the home is complete is treated differently from interest paid after. Under the old tax regime, it is added up and claimed in five equal yearly parts, starting from the year construction is completed. The claim falls within the overall limit of Rs. 2 Lakhs a year for a home the owner lives in.
The new tax regime allows no interest deduction on a self-occupied home. Most salaried buyers on the new regime therefore gain nothing in tax from pre-EMI interest. The comparison between the two routes should be made on cash cost alone.
Questions to Ask Before Signing
A buyer who is offered a builder scheme should ask for the terms in writing. These questions separate a simple deferred plan from a loan with early disbursal:
- Is a loan taken now, or only near possession?
- How much will the bank release before the structure is complete?
- Who pays the interest, until which date, and what happens if possession is late?
- What is the price of the same flat on a construction-linked plan?
- Does the three-way agreement make the buyer liable if the developer misses a payment?
- What are the charges for cancelling the booking or moving the loan to another lender?
The project's registration and quarterly progress on the Karnataka RERA portal show whether the work is on schedule. Under the RERA Act, a developer may take up to 10% of the price before a registered agreement for sale. Any plan that needs more than that before the agreement should be questioned.
Which Route Suits Whom
A construction-linked loan suits most buyers who live on rent and have a steady income. The interest during the build is a real cost, yet the buyer keeps control and the bank pays only for finished work. Our EMI calculator helps to plan the months when rent and pre-EMI interest overlap.
A deferred payment plan from a well-funded developer suits a buyer who expects a large inflow near possession, such as the sale of another home. The higher price is the fee for waiting. A subvention scheme that depends on early disbursal of a loan in the buyer's name is the one to treat with the most caution. Checking the developer's delivery record on a few Bangalore projects is a sensible first step with any of the three.