Three of the main roads in Mysore are due to reopen with new concrete surfaces by 5 October 2026, in time for Dasara. They are Banni Mantap Road, Manandavadi Road and the road at Manipal Junction. The stretches belong to a white-topping project of the Public Works Department (PWD) that covers 12 major city roads, 46.088 km in all, at a cost of Rs. 393.8 Crore.

What opens before Dasara

Work on the three roads began in April 2026 and is in its final stage. PWD Executive Engineer Padmanabha said on 28 September 2026 that concreting of the three stretches ends by 5 October, after which they open to traffic. Dasara runs from 11 to 21 October this year, and the city's roads carry their heaviest traffic of the year in that period.

Before the concrete was laid, the utility lines beneath each road were shifted to its edge. Drainage, water supply, electricity and telecom lines were all relocated, with the departments that own them taking part. The step matters, since a concrete road is costly to cut open and repair once it is finished.

Work paused on the other roads

On the orders of the district administration, white-topping on the remaining stretches stays suspended through the festival. The PWD resumes the pending work once the celebrations end on 21 October. The roads where work is paused or still to be concreted include:

  • JLB Road, between the city railway station and Yelethota Junction
  • Hunsur Road, between Metropole Circle and the Hinkal end at the Outer Ring Road
  • The stretch linking Ramavilas Road with Banumaiah College Junction
  • Irwin Road, KRS Road and Mahadevapura Road
  • Kempegowda Circle to Hardinge Circle
  • Zoo Road and Vishwamanava Double Road
  • The road connecting Mini Vidhana Soudha, and the corridor road at the Karnataka Police Academy

Officials expect the concrete surface to last about 20 years. They also expect it to end the yearly cycle of potholes and to give drivers a clearer view of the road.

What white-topping changes for residents

White-topping places a layer of cement concrete over an existing asphalt road. The result is a harder surface that holds up through the monsoon and needs little patching. The cost is paid during construction: a stretch stays closed or half-closed for months, traffic moves to side streets, and shops along the road lose access for a while.

The first three roads show the gain. Their residents and traders get a finished surface at the busiest time of the year, after about six months of work. The other stretches will go through the same cycle once work restarts.

What it means for home buyers

A concreted main road is a real improvement for the neighbourhoods beside it, since daily travel and drainage along the road both get better. It is a modest one too. The project rebuilds existing roads and adds no new road or lane, so travel distances and the shape of the city stay the same.

Buyers looking at homes off Hunsur Road, KRS Road or JLB Road should expect closures and diversions when work resumes after 21 October. A site visit during the works gives a fair picture of access in that period. The lasting factors in a Mysore purchase remain the same: the approval of the layout or building, clear title, the Karnataka RERA registration of a new project, and water supply.

Frequently Asked Questions

Which Mysore roads will open before Dasara 2026?+
Banni Mantap Road, Manandavadi Road and the road at Manipal Junction. The Public Works Department expects to finish their white-topping by 5 October 2026.
How large is the Mysore white-topping project?+
It covers a dozen arterial roads, 46.088 km in total, at a cost of Rs. 393.8 Crore. The Public Works Department is carrying out the work.
When will work restart on the remaining roads?+
After Dasara ends on 21 October 2026. The district administration has suspended white-topping on the other stretches for the festival period.