Namma Metro Network: Lines Open, Under Construction and Planned

By Bangaloreprop Editorial Team·5 October 2026·7 min read

Namma Metro is now part of almost every property advertisement in Bangalore, but the lines are at very different stages. Three are open, two are being built and two more are approved or proposed. This guide sets out each line in October 2026, the localities it serves and how much weight a home buyer should give it.

The Network at a Glance

Namma Metro has 96.1 km of track and 83 stations in service, run by Bangalore Metro Rail Corporation Limited (BMRCL). The table lists every line by stage, and the sections below add the detail.

LineRouteLengthStage in October 2026
PurpleChallaghatta to Whitefield (Kadugodi)43.49 kmOpen
GreenMadavara to Silk Institute33.46 kmOpen
YellowRV Road to Bommasandra19.15 kmOpen
PinkKalena Agrahara to NagawaraAbout 21 kmElevated part built, awaiting safety clearance
BlueCentral Silk Board to the airport58.19 kmUnder construction
Orange and Magadi Road corridor (Phase 3)JP Nagar 4th Phase to Kempapura, Hosahalli to Kadabagere44.65 kmApproved, at tender stage
Red (Phase 3A)Hebbal to Sarjapura37.8 kmAwaiting central approval

Lines That Are Open

Three lines carry passengers today. A home near one of their stations has a benefit that the buyer is able to test before paying.

Purple Line

The Purple Line runs east to west across the city, with 37 stations. It links Kengeri and Mysore Road with Vijayanagar, Majestic, MG Road, Indiranagar, KR Pura and Whitefield. The eastern stretch from KR Pura to Whitefield opened in March 2023 and changed the commute to the ITPL belt.

Green Line

The Green Line runs north to south, with 32 stations. From Madavara on Tumkur Road it passes Peenya, Yeshwanthpur, Rajajinagar and Malleshwaram, and meets the Purple Line at Majestic. It continues through Basavanagudi, Jayanagar and Banashankari to Kanakapura Road. It serves the older, settled residential parts of the city.

Yellow Line

The Yellow Line opened in August 2025, with 16 stations. It connects RV Road with BTM Layout, Central Silk Board, Bommanahalli, Hosa Road, Electronic City and Bommasandra. Passengers change to the Green Line at RV Road.

Lines Under Construction

Two lines are being built. Both have changed their opening targets more than once, so a buyer should plan the commute on what runs today.

Pink Line

The Pink Line will have 18 stations from Kalena Agrahara on Bannerghatta Road to Nagawara in the north. Its elevated section of 7.5 km and six stations, up to Tavarekere, is built and has completed its trials. Services will begin once the Commissioner of Metro Railway Safety clears the section.

The rest of the line is underground, through Dairy Circle, MG Road, Shivajinagar and Cantonment, and will open at a later stage. The Pink Line will meet the Yellow Line at Jayadeva Hospital and the Purple Line at MG Road. Homes on Bannerghatta Road gain first, and those near the underground stations gain later.

Blue Line

The Blue Line has 30 stations in two parts. The first runs 19.75 km along the Outer Ring Road from Central Silk Board to KR Pura, past Bellandur and Marathahalli. The second runs 38.44 km from KR Pura to the airport through Nagawara, Hebbal and Yelahanka.

BMRCL has moved the start of services on the Silk Board to KR Pura part into 2027, and the airport part will follow. The line will connect with the Yellow Line at Central Silk Board and the Purple Line at KR Pura. Once the Pink and Blue lines are fully open, the network will reach about 175 km.

Lines Approved or Proposed

Two further phases exist on paper and in tenders. They belong in a long-term view of a locality and deserve little weight in the price paid today.

Phase 3: Orange Line and the Magadi Road Corridor

Phase 3 covers 44.65 km and 31 stations, and the Union Cabinet approved it on 16 August 2024. The Orange Line of 32.15 km follows the western Outer Ring Road from JP Nagar 4th Phase to Kempapura, past Mysore Road and Sumanahalli Cross. A second corridor of 12.50 km runs along Magadi Road from Hosahalli to Kadabagere.

The state has decided to build Phase 3 as a double-decker, with a road flyover below the metro track, at an added cost of Rs. 9,700 crore. BMRCL issued the first civil tenders in 2026, and the completion target has moved from 2030 to 2031. Major construction along the alignment will bring several years of road diversions before any train runs.

Phase 3A: Red Line

The Red Line is a proposed corridor from Hebbal to Sarjapura, 37.8 km long in the plan revised in February 2026. Its route passes through the city centre, Dairy Circle, Koramangala and Agara before following Sarjapur Road. The Karnataka cabinet approved it on 6 December 2024, and it is awaiting the approval of the central government.

Cost and design are still under review, so the opening year remains open. For Sarjapur Road, which has no metro station today, the Red Line is a plan and should be read as one.

How Buyers Should Weigh Each Stage

The stage of a line matters more than its length or cost. A simple rule keeps the metro in proportion when comparing two homes.

  • Open line: count it fully, after walking from the home to the station at the hour of the commute
  • Line under construction: count it as a later benefit, and expect dust, diversions and a possible delay until then
  • Approved line at tender stage: treat it as a long-term plus that is many years away
  • Proposed line: leave it out of the price

Distance decides the rest. A station within a ten-minute walk changes daily life, while one that needs an auto or a feeder bus helps far less. Interchange stations such as Majestic, RV Road and KR Pura give access to two lines, which widens the choice of workplaces.

Checks Before Paying for Metro Access

Advertisements often show a station close to the project without stating the line or its stage. Five checks settle the matter.

  1. Name the line and the exact station, and confirm both on the BMRCL route map.
  2. Confirm whether that station is open, under construction or only planned.
  3. Walk the route from the gate to the station entrance, and note the crossings and footpaths.
  4. Ask whether the road in front of the project is on a metro alignment where land is still to be acquired.
  5. Compare the price with a similar home further from the station, to see what the metro is adding.

The home should also work without the line that is still to come. We are glad to share which stations are open near any project on our pages.

Frequently Asked Questions

How long is the Namma Metro network in October 2026?+
96.1 km, with 83 stations on three lines: the Purple Line (43.49 km), the Green Line (33.46 km) and the Yellow Line (19.15 km).
Which Namma Metro lines are under construction?+
The Pink Line from Kalena Agrahara to Nagawara and the Blue Line from Central Silk Board to the airport. The Pink Line's elevated section is built and awaiting safety clearance.
Is the metro to Bangalore airport open?+
Not yet. The Blue Line to the airport through Hebbal and Yelahanka is under construction, and its Silk Board to KR Pura part is due first, in 2027.
Does Sarjapur Road have a metro line?+
Not yet. The proposed Red Line from Hebbal to Sarjapura, 37.8 km long in the revised plan, has state cabinet approval and is awaiting the approval of the central government.
How much should a planned metro line add to a home's price?+
Very little. An open line deserves full weight and a line under construction some weight, while an approved or proposed line is many years away and should not decide the price.