Total Environment in Bangalore: Developer Profile for Home Buyers

Total Environment is a Bangalore developer known for homes that are designed project by project, with gardens on every floor and a great deal of exposed brick, stone and timber. This profile covers the company's background, its projects in Bangalore, the completion dates registered for each phase and the checks a buyer should run before booking. It is written for buyers who like the design and want a clear view of the price and the wait that come with it.
The Company in Brief
Total Environment is an architect-led real estate developer from Bangalore, founded in 1996 by the architects Kamal Sagar and Shibanee Sagar. Kamal Sagar is the chairman and managing director. The company designs its own buildings, runs its own construction and makes much of the joinery and interior work itself. A summary of its homes in the city is on the Total Environment page.
The firm is privately held, so it publishes far less financial information than a listed developer. Its projects are registered under several group companies, among them Total Environment Building Systems, Total Environment Habitat and Total Environment Constructions. The company named in a sale agreement is therefore the one whose registration a buyer should read.
What Sets the Homes Apart
A Total Environment home is easy to recognise. Most apartments open on to a private garden terrace with soil beds and drip irrigation, even on the upper floors. Walls are often left in exposed brick or concrete, and the woodwork, kitchens and wardrobes are usually part of the home that is handed over.
Projects carry the names of songs and books, such as After the Rain, Windmills of Your Mind and In That Quiet Earth. Layouts are large, and many homes include a study, a home office or a staff room. Buyers are generally offered a choice of interior finishes, which adds design work and time to each home.
The same approach explains the price. Homes from this developer are sold in the luxury segment, and the rate reflects finished interiors, the garden terraces and lower density than a standard tower. A fair comparison with another project therefore counts what is included in each home, as well as the rate per sq ft.
Projects in Bangalore
The company's work is spread across the east, north and south of the city. The main communities are these:
- Windmills of Your Mind, Whitefield: a completed community of apartments and villas
- Pursuit of a Radical Rhapsody, Whitefield: high-rise apartments built in phases, with some towers still under construction
- After the Rain, Yelahanka: villas and apartments built in several phases
- In That Quiet Earth, off Hennur Road: apartments in phases, with the last tower registered in 2025
- Down by the Water, Jakkur: apartments registered in August 2024
- The Magic Faraway Tree, Kanakapura Road, and Learning to Fly, JP Nagar: apartment projects in the south
- Tangled Up in Green, Devanahalli: a plotted development registered in January 2024
- Over the Rainbow, near Nandi Hills: a villa project in Chikkaballapura district
Registered Completion Dates, Phase by Phase
Design-heavy homes take longer to build, and the registered dates reflect that. Each phase of a project has its own registration on the Karnataka RERA portal, with its own completion date. Several older phases have had that date moved forward more than once, which is the main point a buyer should understand before booking.
The dates on the portal on 3 October 2026 were as follows:
| Project and phase | Registered | First completion date | Current completion date |
|---|---|---|---|
| After the Rain Phase 1 | October 2017 | 30 June 2019 | 30 April 2022 |
| After the Rain Phase II A | May 2018 | 31 December 2022 | 30 September 2024 |
| After the Rain Phase IIB | October 2019 | 1 November 2024 | 1 August 2026 |
| After the Rain Phase IIC | March 2022 | 1 April 2028 | 1 April 2028 |
| After the Rain Phase III | August 2025 | 30 April 2032 | 30 April 2032 |
| Pursuit of a Radical Rhapsody Phase 1 | October 2017 | 31 July 2024 | 30 April 2027 |
| Pursuit of a Radical Rhapsody Phase 2 | January 2019 | 30 June 2026 | 30 March 2027 |
| Pursuit of a Radical Rhapsody Tower 8 | September 2022 | 30 September 2029 | 30 September 2029 |
| Pursuit of a Radical Rhapsody Tower 5 | December 2022 | 1 December 2029 | 1 December 2029 |
| In That Quiet Earth (first phase) | May 2018 | 31 December 2025 | 30 September 2026 |
| In That Quiet Earth Phase 2a | October 2020 | 31 December 2025 | 31 December 2026 |
| In That Quiet Earth Phase 2B | July 2022 | 1 May 2028 | 1 May 2028 |
| In That Quiet Earth Phase 2C | April 2024 | 31 March 2031 | 31 March 2031 |
| In That Quiet Earth Tower 8 | January 2025 | 31 December 2032 | 31 December 2032 |
| The Magic Faraway Tree Phase 2 | October 2017 | 31 December 2023 | 30 September 2027 |
| The Magic Faraway Tree Phase 2a | December 2018 | 31 December 2024 | 30 September 2026 |
| Learning to Fly | October 2017 | 31 December 2023 | 30 September 2024 |
| Down by the Water | August 2024 | 31 May 2031 | 31 May 2031 |
| Tangled Up in Green | January 2024 | 31 December 2028 | 31 December 2028 |
| Over the Rainbow Phase 1 | April 2024 | 28 February 2030 | 28 February 2030 |
Two patterns are clear from the table. Phases registered in 2017 and 2018 have mostly seen their completion dates extended, in a few cases by two to four years. Newer phases carry long timelines from the start, with registered dates between 2028 and 2032.
What the Timelines Mean for a Buyer
A long build changes the cost of a home, even when the price is fixed. A buyer who pays rent and a home loan instalment together carries both for the whole construction period. Under a construction-linked plan the loan is drawn in stages, so the interest paid before possession grows with every extra year. The site's EMI calculator helps to size the instalment before a booking.
The registered completion date is the one to plan around, since it is the date the promoter has committed to under the Act. A sale agreement should carry the same date as the registration of that phase. Where a date has passed, the Act gives the buyer a right to interest for the delay or to a refund with interest.
Resale needs some thought as well. A highly individual home appeals strongly to some buyers and less to others, so a sale may take longer than it would for a standard apartment. The high ticket size also narrows the number of buyers at any one time.
Who These Homes Suit
These homes suit a buyer who plans to live in the home for many years and values design, gardens and finished interiors above an early move-in date. They also suit a family that already owns a home and is able to wait for the next one. A buyer who needs possession by a fixed date is better served by a completed home from this developer or a ready project elsewhere.
Checks Before Booking
The checks below apply to any Total Environment home, whether new or resale:
- Find the exact phase or tower on the Karnataka RERA portal and note its registration number, promoter company and completion date
- Read the quarterly progress updates filed for that phase and compare them with the work visible on site
- Ask for the carpet area of the home in sq ft, with the garden terrace area stated separately
- Get a full cost sheet that lists GST, parking, club charges, interior options and maintenance deposits
- Match the possession date and the delay clause in the sale agreement with the registered date
- For a completed home, ask for the occupancy certificate and the khata of that block
- Visit a completed community, such as Windmills of Your Mind, to see how the finishes and gardens age
Buyers comparing developers will find the same checks useful elsewhere. A project page on this site lists the registration number where one is available, and our team is glad to share the latest price list for any Total Environment project.